Forum Discussion

BlissL's avatar
BlissL
Brass Contributor
Sep 11, 2022
Solved

Auto-submission of task updates and approvals in PWA

Hi all,    I've set up a rule to set up auto approvals for task updates as the projects managed are separate to the financials, so approval is not required.  However, when users mark their t...
  • Dale_HowardMVP's avatar
    Sep 12, 2022
    BlissL --

    When a user clicks the Save button, all this action does is to save the latest task status changes to the Project Online database. When the user clicks the Submit button, this action submits the task updates for approval by the relevant project manager. So, no, your team members will need to submit their task updates regularly rather than merely saving them. Hope this helps.

Resources