Forum Discussion
Jhonex1
Jun 27, 2022Copper Contributor
Assigning cost resources to summary task is grayed out
Hi,
I am trying to assign a cost resources to the summery task which I created in resources sheet as "Cost" and gave a group name. I turn into gantt chart and try to assign the resources to the summary task. I noticed that the assign button is grayed out. rest of the resources are good to assign.
Please advice what is the fix for this issue.
I am using MSP 2016.
Thanks
Jhonex1 have you got the Summary tasks option checked under Gantt Chart Format?