Assigning Calendar
I want to assign a calendar by default whenever I add a new activity to existing project. I have created separate calendar based on my project needs but whenever new activity is added, the calendar shown is "None". What could be done so that every new activity added will have a calendar of project.
- Hi Kedar.
Add this new custom calendar to the project in: Project > Properties > Project information, or modify the Standard calendar that is assigned by default.
When None appears in the task calendar, and although the word is not appropriate, the calendar that is assigned to the project is the same calendar that is assigned to the task.
Ignacio M.
1 Reply
- Ignacio_MartinIron ContributorHi Kedar.
Add this new custom calendar to the project in: Project > Properties > Project information, or modify the Standard calendar that is assigned by default.
When None appears in the task calendar, and although the word is not appropriate, the calendar that is assigned to the project is the same calendar that is assigned to the task.
Ignacio M.