Forum Discussion
Alert - external linkn
Hello Inquisitore
Many times, the warning comes from a residual link in the metadata, try the following:
Save the file as Project XML (.xml).
Close Project.
Open the newly saved XML.
Save again as .mpp.
This process usually "cleans up" invisible or broken links.
I hope you find it helpful.
Ignacio
- inquisitoreAug 18, 2025Copper Contributor
No it does not work, the project is without tasks, I erased all tasks to check if problem persists.
- John-projectAug 19, 2025Silver Contributor
Inquisitore,
I thought Ignacio had a great suggestion, sorry it didn't work.
I have the same configuration you have, but for reference, what is your version of Project? The latest is: version 2507 (Build 19029.20184). If that is not your version I suggest you update.
I take it you can open the file, you just get the unfriendly message. Is that correct? If so, open the file and go to, developer > Code group > Visual Basic. In the VBE window open the Project Explorer and double click on "ThisProject (name)". Does anything appear in the code window? If so, select and delete it.
If necessary, would you be able to send me your file? I can give you m
John