Adding Status marker in Burndown Report
Hi all,
first time poster and new user to Microsoft project.
I have created a Burndown report and I am wanting to add in a Status Marker or todays date marker to my report that will move with time . Can this be done?
Or do I need to manually insert a shape and create my own marker? And then I will have to move it every time I status or need to show the report to anyone?
Thanks!
6 Replies
- John-projectSilver Contributor
Can it be done? Possibly, but to automate the process (e.g. dynamically move the marker with the current date or status date) requires some VBA. I've never done something like that before so I'd have to do more research.
John
- MichelleblogsCopper Contributor
hey John! Okay great, gives me some hope! Will be interesting to know if and how it can be done - thanks in advance for your help
thanks
- John-projectSilver ContributorMichelleblogs,
Don't hold your breath waiting for me to come back with something, I've got several things "on my plate".
I like Ismet's suggestion of using a secondary axis as it shows a nice vertical marker which may not be that easy to produce with a manually drawn line.
John