Forum Discussion
SayedNasr
May 22, 2023Brass Contributor
Adding Multiple choice columns to Tasks in P4W
Hello guys, I need to add multiple choice columns to Project for The Web "Tasks" with cascading behavior; selecting an option from one choice column shall limit the options listed in subsequent c...
May 22, 2023
SayedNasr --
What you want to do cannot be done currently in Project for the Web. Nor could it be done in the Microsoft Project desktop app either. In either application, it is not possible to select a value from a pick list in one column, and then to display a customized list in the second column, based on the value selected in the first column. Furthermore, you cannot import a project from an Excel workbook into Project for the Web. Sorry, but hope this helps.
What you want to do cannot be done currently in Project for the Web. Nor could it be done in the Microsoft Project desktop app either. In either application, it is not possible to select a value from a pick list in one column, and then to display a customized list in the second column, based on the value selected in the first column. Furthermore, you cannot import a project from an Excel workbook into Project for the Web. Sorry, but hope this helps.
- SayedNasrMay 22, 2023Brass Contributor
Thanks Dale. It's disappointing how P4W is built on a fully customizable platform like power apps -at least as per MS claims- but we stuck in such simple customization needs.