Adding Multiple choice columns to Tasks in P4W
Hello guys, I need to add multiple choice columns to Project for The Web "Tasks" with cascading behavior; selecting an option from one choice column shall limit the options listed in subsequent c...
SayedNasr
May 22, 2023Brass Contributor
Searching if anyone had faced same issue, I found that:
- Adding custom fields from Task Grid won't help. You can export Task list from Task Grid with all fields including the custom ones you add manually from the grid but it'll not reflect to the "Project Task" Dataverse table. Then, you can't recall such custom fields on Power BI for example or other apps.
- Adding custom fields through the Power App interface itself can't be shown in the "Task Grid"
Is forking the Task Grid and having my version of it an option?