FabioBrandao Sometimes it's different way between Project Online and Project Server. I think your code is for Project Online and not for Project Server. Have you try by using this reference?
https://vamsi-sharepointhandbook.blogspot.com/2016/06/project-server-2013-build-project-team.html
- FabioBrandaoOct 09, 2020Copper Contributor
Ade_Budiman_Lim no, it's on an On Premisse environment. And it is an unaccepted bug from Project Server CSON on PowerShell. I made a mistake talking about my goal to support of Microsoft, and after that they sad repeatedly "It will not work" referring to my goal, and not accepting the point I exposed on this post. I'm very frustrated every time I report things like that and they sidetracking me (this case took around 5 month to at the end I say "you will not focus on my problem and don't stop saying 'it will not work', close this case please.")
It is a bug, period. But they can't see it.
The solution was go to C#. There, exactly the same logic (creation of objects, callings and attributions) and it worked very well.
PS: Today I don't know if it was fixed on PowerShell.