Forum Discussion
James_Price
Mar 10, 2023Copper Contributor
Add a 2nd project manager...
Hi team I need a 2nd PM to be able to access a POL project. Naturally they have a Project Plan 3 licence, POL permissions have been set and in security groups they are PM and Team Member. I though...
- Mar 10, 2023James --
You can do this through Project Permissions. Log into PWA and navigate to the Project Center page. At the far left end of the line for the project in question, click the row header to select that project. In the Projects ribbon, click the Project Permissions button. On the Permissions page, click the New button. On the Edit Project Permissions page, add the second PM to the list on the right and then select ALL of the checkboxes at the bottom of the page. Click the Save button. Now the second PM should be able to see, open, check out, edit, save, and publish the project in question. Hope this helps.
Mar 10, 2023
James --
You can do this through Project Permissions. Log into PWA and navigate to the Project Center page. At the far left end of the line for the project in question, click the row header to select that project. In the Projects ribbon, click the Project Permissions button. On the Permissions page, click the New button. On the Edit Project Permissions page, add the second PM to the list on the right and then select ALL of the checkboxes at the bottom of the page. Click the Save button. Now the second PM should be able to see, open, check out, edit, save, and publish the project in question. Hope this helps.
You can do this through Project Permissions. Log into PWA and navigate to the Project Center page. At the far left end of the line for the project in question, click the row header to select that project. In the Projects ribbon, click the Project Permissions button. On the Permissions page, click the New button. On the Edit Project Permissions page, add the second PM to the list on the right and then select ALL of the checkboxes at the bottom of the page. Click the Save button. Now the second PM should be able to see, open, check out, edit, save, and publish the project in question. Hope this helps.
Robinjvv
Jun 27, 2023Copper Contributor
Hello Dale, hope you are well! I have done this too, The second PM can do everything except build team. Any ideas on what could be the issue?
- Jun 28, 2023Robinjvv --
The problem is likely caused by the security Group to which the second PM belongs. Without seeing the setup of your Project Online system, I cannot troubleshoot the problem any further. Hope this helps.