LucaGunetto
Jun 05, 2023Copper Contributor
Activities status
Hello everyone, I know that could be easy for some of you but my problem is the following: I have a series of ongoing tasks and I want to update automatically the percentage of completion of ...
John-project
Jun 05, 2023Silver Contributor
Luca,
As Dale noted, Project has no functionality to do the type of custom automation you want. It could be done with a VBA macro. However, I question the validity of automatically claiming progress on any task, that isn't reality.
John
As Dale noted, Project has no functionality to do the type of custom automation you want. It could be done with a VBA macro. However, I question the validity of automatically claiming progress on any task, that isn't reality.
John