Accounting Project Manager's Time in the Project Plan
HI I have the following scenario. I have a PM whose annual salary let say is $120K and his salary is coming out from the project budget that he is managing. In the project plan the PM is also ass...
Mar 16, 2021
Kish27 -- Set the Standard Rate for the project manager to $0/hour. Then use the Fixed Cost of $120,000 as you stated. Hope this helps.
- Kish27Mar 16, 2021Copper ContributorHo Dale
Thanks for your reply. Yes I could do what you suggested. Is this the best way to do this? What is the industry practice on this issue.
Best Rgds