Forum Discussion

ACSkoz's avatar
ACSkoz
Copper Contributor
Feb 02, 2022

Accounting For Known Delay's When Planning a Project

I am a PM for a construction company and I'm trying to find the best, or most appropriate way to insert days for subcontractors I know are going to be late to start their work.  All of our subs sign ...
  • John-project's avatar
    John-project
    Feb 03, 2022
    ACSkoz,
    As I said there are two ways to handle the uncertainty of subcontractor start dates, with a constraint or with a lag. Normally constraints are not good practice as they disrupt the schedule dynamics (i.e. non-continuous logic path) but if there is no valid predecessor task, putting a start constraint is the best option.

    I see in your schedule you have chosen to use lag but I question whether the predecessor upon which you added the lag is indeed valid. For example, is plumbing really a driver for the mechanical work? Certainly plumbing drain lines have slope requirements to work properly but duct work normally requires the most free space in limited chase runs. The point is, links between tasks should be true requirements not just for convenience.

    With the constant change and uncertainty in construction, I think your best bet is to make your best guess on subcontractor start dates based on your experience with each subcontractor. If you try to keep up with constantly changing estimates you will spend a lot of frustrating time scheduling.

    As far as a "more proper" way of handling schedule delays, I think you have a good handle on it, so press on and good luck with your plan.
    John

Resources