Forum Discussion
PowerFanAddict
Sep 02, 2021Copper Contributor
Accessing Project Custom Fields in Power Automate
Hi I have created some custom fields in my project and I'm trying to create a link to a SharePoint list using Power Automate. I am able to access the out of the box fields in the flow via the Dat...
- Sep 03, 2021
Hello PowerFanAddict ,
Custom fields added to Project for the web Project UI are not available directly in Tables in Dataverse so will not be accessible via Power Automate unfortunately.
Paul
Paul_Mather
Sep 03, 2021MVP
Hello PowerFanAddict ,
Custom fields added to Project for the web Project UI are not available directly in Tables in Dataverse so will not be accessible via Power Automate unfortunately.
Paul
- cgangwegJun 06, 2024Copper Contributor
Unfortunate. Any ideas for another connector that would be able to query for a project/planner custom field?
- SayedNasrMay 22, 2023Brass ContributorHi Paul, could you elaborate more where custom fields data are stored if not on Dataverse ?
- Paul_MatherMay 23, 2023MVPThey are stored in the Project service but not in Dataverse, they are not accessible you outside of the Project UI.
- PowerFanAddictSep 04, 2021Copper ContributorHi Paul - Thank you for the clarification