A Pop up for Impacted Milestones
Hi, I have a project file with over 2000 lines of interlinked tasks and milestones. The milestones are spread across those 2000 lines. A top summary task of "Milestones" is created, which is a g...
- Dec 01, 2023Hi NKumar
About point 1, I think there is no option you are looking for, except by running a macro.
Likewise, with point 2, it would be possible through a macro, although you would have to press a button before entering the data, and I don't know if that is useful to you.
Regards
Ignacio_Martin
Dec 01, 2023Iron Contributor
Hi NKumar
About point 1, I think there is no option you are looking for, except by running a macro.
Likewise, with point 2, it would be possible through a macro, although you would have to press a button before entering the data, and I don't know if that is useful to you.
Regards
About point 1, I think there is no option you are looking for, except by running a macro.
Likewise, with point 2, it would be possible through a macro, although you would have to press a button before entering the data, and I don't know if that is useful to you.
Regards