% Work completed and Status Update (MS Project 2019)

Hi,

 

The % work completed in Project Overview report and the % of status of completed task in Late Report are different, why?

 

% Complete

% Work Complete

17%

17%

 

 

Thanks.

Teshome

1 Reply

  • ismet_kocaman's avatar
    ismet_kocaman
    Brass Contributor

    Sorry, better answer late than never...
    Graph shows the percentages based on the number of status labels such as X percent of the tasks have the status "Complete". So what I see is most of them are the future tasks.