% Work Complete Status
A have a project plan and had about 300 lines as was progressing through project the % Work complete was showing as 20%. I have added a further 200 lines, and increased the length of the project. T...
- Aug 30, 2022parlisingn,
Duration doesn't necessarily "map" back to actual work. For your server example, it sounds like you should use fixed duration as your task type. Duration is entered as a week. The 3 hours of labor (work) to accomplish that task may be linearly spread over the week, occur all on the first day, all on the last day or any combination thereof.
John
John-project
Aug 30, 2022Silver Contributor
parlisingn,
Duration doesn't necessarily "map" back to actual work. For your server example, it sounds like you should use fixed duration as your task type. Duration is entered as a week. The 3 hours of labor (work) to accomplish that task may be linearly spread over the week, occur all on the first day, all on the last day or any combination thereof.
John
Duration doesn't necessarily "map" back to actual work. For your server example, it sounds like you should use fixed duration as your task type. Duration is entered as a week. The 3 hours of labor (work) to accomplish that task may be linearly spread over the week, occur all on the first day, all on the last day or any combination thereof.
John
parlisingh
Aug 31, 2022Copper Contributor
thank you,
- John-projectAug 31, 2022Silver Contributorparlisingh,
You're welcome and thanks for the feedback.
John