!! Problème affichage courbe avancement MS Project !! URGENT
Lorsque je veux imprimer un planning, il y a un problème d'affichage avec la courbe d'avancement. Avez-vous des solutions pour pallier à ce problème s'il-vous-plait ? Cordialement Demande urge...
John-project
Feb 03, 2022Silver Contributor
Loick_Blaisseand others,
This is a confirmed issue with Project 2019. Project developers are aware of this problem but have not released any information about if and when the issue will be resolved.
Test results with the latest update (Version 2201 Build 14827.20158 Click-to-Run) show some improvement depending on paper size selection and orientation.
John
Loick_Blaisse
Feb 04, 2022Copper Contributor
So are we paying licenses for getting this kind of issues ? Your answer is more that disappointing, I've already spent many hours trying to solve this.
Hope it's going to change fastly.
Hope it's going to change fastly.
- John-projectFeb 04, 2022Silver ContributorLoick_Blaisse,
Bear in mind that neither I, nor others who normally respond to questions on this forum, work for or have any affiliation with Microsoft. We simply lend our expertise and knowledge to help other users.
Progress lines are not the only way to graphically show progress. If you can be more specific about your needs, we can recommend other approaches as a workaround.
John- Loick_BlaisseFeb 04, 2022Copper ContributorSorry for this, thank you for your help.
I want to show in a very simple way which task is critical, compare to the day we are. i don't need to be very accurate (for example no % numbers) but i want it to be intuitive.- John-projectFeb 04, 2022Silver ContributorLoick_Blaisse,
Project already has a couple different way to show critical tasks. You can add the Critical field to the view and/or display critical tasks via, Gantt Chart Format > Bar Styles group > Critical tasks.
In the following post I include a workaround for progress bars.
https://answers.microsoft.com/en-us/msoffice/forum/all/project-2019-progress-line-printing-issues/c0e73ae2-19bd-41bd-bc4c-27f55ba58a90
John