Forum Discussion

tanzimshaikh's avatar
tanzimshaikh
Brass Contributor
Aug 01, 2024
Solved

% Complete and Planned % Complete is not same

Hello Experts, I have a scenario where I am running a project. Following is the implementation of the same:   There are no dependencies in the project and neither the baselines for my projec...
  • John-project's avatar
    John-project
    Aug 08, 2024
    tanzimshaikh,
    You say you need % complete and planned % complete at summary level to be the same. Why? Typically they will not be the same even if calculated in the same manner. Percent complete is independent of the status date whereas any planned percent complete calculation at summary level will be dependent on the status date.

    Percent complete at summary level, whether calculated by Project using the formula Ignacio presented, or calculated via a custom formula/process, is dubious at best. In other words, summary level percent complete is highly subjective. In fact, percent complete based on duration is in my view pretty meaningless since the passage of time (duration) doesn't accomplish anything, unless its paint drying, concrete curing, or a wound healing.

    In your screen shot you show three custom number fields. What exactly do each of them represent (i.e. formulas)? And how do you calculate Planned % Complete at summary level?

    John