Forum Discussion
tanzimshaikh
Aug 01, 2024Brass Contributor
% Complete and Planned % Complete is not same
Hello Experts, I have a scenario where I am running a project. Following is the implementation of the same: There are no dependencies in the project and neither the baselines for my projec...
- Aug 08, 2024tanzimshaikh,
You say you need % complete and planned % complete at summary level to be the same. Why? Typically they will not be the same even if calculated in the same manner. Percent complete is independent of the status date whereas any planned percent complete calculation at summary level will be dependent on the status date.
Percent complete at summary level, whether calculated by Project using the formula Ignacio presented, or calculated via a custom formula/process, is dubious at best. In other words, summary level percent complete is highly subjective. In fact, percent complete based on duration is in my view pretty meaningless since the passage of time (duration) doesn't accomplish anything, unless its paint drying, concrete curing, or a wound healing.
In your screen shot you show three custom number fields. What exactly do each of them represent (i.e. formulas)? And how do you calculate Planned % Complete at summary level?
John
tanzimshaikh
Aug 04, 2024Brass Contributor
Anyone on this please. Why are the percentages different?
John-project
Aug 04, 2024Silver Contributor
Sorry, but without a baseline there is no "planned % complete".
Ignacio already gave you the formula Project uses to calculate percent complete at summary level. To replicate that in a formula you will have to create a couple of custom duration fields that sum up the Duration and Actual Duration field to summary level and then use a third custom field to implement the formula Ignacio gave you.
But instead of that, I suggest you take a look at the following article:
https://mpug.com/planned-and-actual-percent-complete-in-ms-project/
John