Forum Discussion
Hogstad_Raadgivning
Dec 01, 2020Steel Contributor
Red arrow between two steps in Power Automate.
Hi,
What is the reason for a red red arrow between two steps?
The Workflow is teh template where you should add a task in Planner from a SharePoint list.
Best Regards
- Geir
1 Reply
Sort By
- iharshalcCopper ContributorHello Geir,
You probably have set "configure run after" options for the step as "failed" "skipped" or "timed out" instead "succeeded" thats why red arrow is there. Could you please check once ?