Weekend Start Date - Planner
Tell me I am missing something weird. I have Planner 1. We have an event on a weekend. Planner tells me that this is an impossibility as no-one works on a weekend. How do I correct this. Thanks
psawyer
Nov 24, 2025Iron Contributor
You have to change the calendar. I am not exactly sure where that setting is in a default environment, but you need to change the calendar to one with a 24 hour work week.