Turn off Completed in Status

is it possible to turn off completed tasks in the status chart? There's no point in seeing all of the many task we have completed when what we really want to see is what's in progress, what's late, and what hasn't started yet. 

2 Replies

  • ben_howard's avatar
    ben_howard
    Copper Contributor
    If you use Power BI you export the plan(s) to Excel and then use this Power BI file https://gallery.technet.microsoft.com/Planner-Charts-56ca3ac4 and use a filter to filter out the completed tasks.