Forum Discussion
To-Do and Planner integration does not work for tasks assigned to multiple people
The integration of Planner and To-Do is a welcome addition but it appears this does not work when tasks are assigned to more than 1 person.
I have a few plans for different Teams and some of the tasks I am undertaking require collaborative work. It appears when a task is assigned to more than 1 person, it does not appear in the 'Assign to me' list and I cannot find it anywhere in To-Do. Am I missing something or has anyone else experienced this?
Note, I have raised this issue with support.
- ben_projectBrass Contributor
DarylAHi, I cannot reproduce your problem - if it is assigned to two people it appears in the "Assigned to me" within ToDo. Note that when one person says it is done, it is set to completed in Planner.
- DarylABrass ContributorThanks for testing ben_project. Unfortunately I am still experiencing the issue. Could it be due to some other reason?
- ben_projectBrass Contributor
DarylAHi Daryl, not that I am aware of. If MS provide you with an answer, please be kind enough to share it here so that others can learn from it.