Forum Discussion
Tom_Hagy
Jan 26, 2021Copper Contributor
Task Checklists Do Not Copy
I love that you can copy tasks from one planner bucket to another, but when I try it the checklists do not carry over. They appear for a second then vanish. Does anyone else have this problem? Is there a fix?
2 Replies
- Tom_HagyCopper Contributor
BTW. I figure out a workaround if anyone has this issue.
- I copy a Task within Bucket A.
- Then MOVE the copied Task to Bucket B.
That brings over all assignments, attachments, checklists. I was trying to copy a task, then re-assigning it to Bucket B. I was losing checklists.
Problem solved.
- AmyncopeCopper ContributorI would love for there to be a way to copy an entire checklist to another card. For instance if we have an entire checklist for a procedure - to be able to move that onto an active card. Would be great, but I cannot find a way to do it (was simple in Trello).