Forum Discussion
DC99
Jan 23, 2026Copper Contributor
Scheduling for public/bank holidays
Is there a way in Planner (Plan 3) where public holidays can be added to the projects calendar and can be selected under the “choose from template”. I’m wanting a plan that takes into account public holidays when scheduling the duration of the tasks.
1 Reply
- JM5Copper Contributor
If you have installed the project accelerator powerapps apps, 'project' and 'resource scheduler' you can add business closures to your calendars in 'resource scheduler'>settings > business closures.