Forum Discussion
Resource calendars
Thanks, that's helpful. It seems the key is getting my IT to allow schedule mode override. If I understand correctly, when that happens and when I create a new plan with fixed effort, then a test would work as follows:
* My calendar is set to 8 hours of availability. I create a Task with a total effort of 8 hours and assign it to myself. Planner gives it a duration of 1 day. If I then reduce my availability by 1 hour, then Planner will maintain 8 hours of effort and cause the task duration to span into a second work day. Or, if I increase the duration to 2 days, Planner will split the 8 hours between both days. Or, if I assign a second resource to the task, Planner would split the fixed work between both resources not to exceed their respective calendar availabilities. Correct?
I looked closer at the Assignments tab, and see how it's possible to manually adjust effort on a daily basis for a resource. That probably is a more workable solution for my case even within fixed duration mode. Plus, it allows me to take into account the reality where a resource works an 8-hour day on the calendar but is only fractionally available to the project due to carrying a portfolio of multiple projects.