Postpone tasks with dependencies
Hey folks, When you postpone a maintask in asana the subtasks automatically change the start and end date as well. I was wondering if Planner 2.0 provides the same feature. Thank you in adva...
- Feb 28, 2024
dschweingruber1205 Hi, it happens as you set dependency between tasks. When parent tasks move, it child tasks dates gets moved automatically. Indeed this feature is available in Planner premium (planner v2.0). You need to have Project license in order to use this in Planner.
Alternately, you can try Apps4.Pro Planner gantt app. This app allows to set dependency between tasks use all features as in Project app.