Forum Discussion
Planner Task Due Dates
Kellijoyrivera nailed the cause - and the reason it behaves that way is worth spelling out, because it also decides how you fix the tasks that are already wrong.
Planner stores every due date as a full timestamp in UTC, even though the screen only ever shows you the date - that's how it's documented in the Planner task reference. So when your flow creates a task from the SharePoint row, whatever time rides along with that date is what gets stored. If it's midnight, or an early-morning time, the task is already past due the moment that time passes, even though the date on the card is still today. The dates are right; the hidden times aren't. That's why the Today bucket emptied out and Past Due filled up.
For the flow itself, Kellijoyrivera's fix is the one: set the due time explicitly when the task is created, late in the due day, and pass it in UTC so the conversion doesn't push it onto the previous day.
For the tasks that are already sitting in Past Due, you don't have to touch them one by one. The Planner connector has an Update a task action with a Due Date Time field, so a one-off flow can list the tasks in the plan and reset their due times to late in their due day in one pass. Try it on a small batch first to confirm the bucket behaviour, then run the rest.