Forum Discussion
Lasse_Jagschies
Jun 11, 2024Copper Contributor
Planner Premium <% complete> calculation is strange
Hi, I encountered a strange behavior of the <% complete> field in the premium planner when you change the <duration> and/or <effort> fields after you started a task, e.g. Set <start date>=today, <...
Lasse_Jagschies
Nov 12, 2024Copper Contributor
Hi Andrew,
Unfortunately, there was no reaction so far. The post probably doesn't have enough votes to be recognized. I'm still interested to get some feedback, just don't know how to push this?!?
Cheers, Lasse