Missing functions in Planner for a Project Manager
Looking at integrating Planner as the company project management tool. One big issue is you can't create your own templates of a standard project plan. You can by pass this by creating a plan and nam...
M_Altobelli
Aug 25, 2025Copper Contributor
If you have to reset every date in your plan in Planner Premium when you copy a project then you need to start using dependencies. That's the point, you change the start date (or some other date) and all the other dates in the plan move accordingly based on the durations of the tasks. You also need to make sure there are no constraints on any of your tasks so they can move freely as needed.