I am trying to develop a way of tracking project and team metrics using the task data in Planner. Does anyone have recommendations for this? Here are a few of the issues: On the task screen, P...
JM5
Mar 10, 2026Copper Contributor
Scheduling includes duration, effort and contouring.
50% complete is not half of the total effort but a midpoint between the start and finish date time of a task. It represents a point in time. From the information above it looks like the schedule has been contoured (weighted towards the end of the schedule).
It's worth doing a deep dive into the scheduling engine.