Is it possible to connect planner to milestones?
Is it possible to connect planner and milestones? So that I can track my planner status in milestones?
- Aug 05, 2021
Sophie_Bruehl- Milestones creates a couple of Dataverse for Teams (D4T) tables in the 'current environment' (i.e. your Team). You will likely need to make at least 2 Power Automate 'flows' for it to work as you would like.
- When you create a task in 'Milestones' through the Power App
- When you create a task in 'Planner' (Teams/Planner.com)
Basically you'll need to create the 'flows' for all the CRUD (create/read/update/delete) operations so that whichever interface is used the desired effect will occur.
There maybe some samples in the Power Automate Community which you can reference.