Forum Discussion
ProjectWiz
Aug 25, 2025Copper Contributor
How do you manage risks in Planner?
Hi All, I tried searching, but couldn't find anything on how to manage risks in Planner. Any ideas or guides out there? Thanks.
pradejain
Aug 25, 2025Iron Contributor
ProjectWiz There is no out-of-the-box feature in the planner to manage the risks. You can try this
In Planner, make each risk a task, group them in buckets by priority (High/Med/Low), use labels for type, and put mitigation steps in the task’s checklist.
Please like and mark it as resolved if it answers your question.
ProjectWiz
Aug 25, 2025Copper Contributor
Wow, very unfortunate. Yes, this is what I have been doing, but I do not like it at all. It clutters my IMS, and I have to create tons of custom fields for scoring. This is PM 101, and there is no out-of-the-box feature.