Forum Discussion
lota
Jul 29, 2025Copper Contributor
Cannot add dependency with task has Effort value
Hello team,
I would like to ask is this default behavior of Planner or bug?
I created a task A, a task B. Both set duration to 1 day.
- Task A will be set: start is Jul 29, finish is Jul 29
- Task B will be set: start is Jul 29, finish is Jul 29
Then input Completed effort for task B is 3 hours. Then set dependency for task B is FS (or any kind of dependencies) to task A.
But task B is still keep Jul 29, expected is Jul 30.
If I clear all Completed effort, it will automatically change to Jul 30.
Thanks
No RepliesBe the first to reply