Bulk import of Tasks in the Premium Planner [not supported] - Any workarounds?
I am trying to simply bulk add tasks to a Planner Project. They have removed the Excel import capability, but you can export. If you cannot use to restore then much efficiency is lost. You can n...
Dec 09, 2025
Using Power Automate cloud flows to create premium plan tasks is technically possible, just way too complex for the average power user. You'll have to call the Project Scheduling Service API via Dataverse actions and get that system to create/update the tasks. It can be done and I've done it, but it's not exactly a fun exercise. I've written about the general requirements and reasons behind this clumsiness here: https://www.perspectives.plus/p/microsoft-planner-and-the-revenge-of-ms-project