We have a customer that wants to move between Office 365 tenants, but has heavily invested in Planner over the past few months. Is there a way using the Microsoft Graph to export/import the buckets ...
- Jan 19, 2017Yes, possible. https://graph.microsoft.io/en-us/docs/api-reference/beta/resources/task If you are looking for an easier way, you can try Apps4.Pro Planner Outlook add-in which allows you to export / import tasks using excel.
SanthoshB1
Jan 19, 2017Bronze Contributor
Yes, possible. https://graph.microsoft.io/en-us/docs/api-reference/beta/resources/task If you are looking for an easier way, you can try Apps4.Pro Planner Outlook add-in which allows you to export / import tasks using excel.
- Jan 19, 2017Thanks Santosh. Can it bring over permissions, checklists, comments or any attachments within those tasks?
- SanthoshB1Jan 19, 2017Bronze Contributor
Hi Loryan Strant, We have not yet supported complete Plan migration. But you can able to Export / Import tasks from plans. All tasks fields are supported in Export / Import.
Exceptions:
- You can able to export comments to excel but cannot import because of API limitation.
- Attachments will be exported as links. You need to change those links with new storage location during import.If you need any corrections to use this, please let me know.
- Samuel WalkerFeb 16, 2018Brass Contributor
I think this is wrong - there's no way to export tasks from plans currently.