Hi,
How can I merge the 2 dates of the same resource into one axis (one row) and not 2 separate rows on the graph? At the moment my view is as follows:
I want it to be presented to me in one axis.
Thanks.
Hi Zahav2335
You may put the durations, and the time between, on top of each other (stacked bars) and set the blocks you want hidden without Fill Color.
Below with and without colors changed.
7 Replies
- bosinanderIron Contributor
Hi Zahav2335
You may put the durations, and the time between, on top of each other (stacked bars) and set the blocks you want hidden without Fill Color.
Below with and without colors changed.
- Zahav2335Copper Contributor
Thank you very much for your input. it is very helpful.bosinander