Forum Discussion
Grace S
Apr 13, 2018Copper Contributor
Help with Workday formula
 Hi,   I am having issue with the workday formula calculating 1 Jan 2018 (which is also bank holiday) to show next working day.     For example:  A1: 01/01/2018  A2: 01/01/2018 (holiday)  A3: =WORKDAY...
SergeiBaklan
Apr 13, 2018Diamond Contributor
Hi Grace,
That's correct result - after Mon, 01 Jan the next working day is Tue, 02 Jan since it's not day-off (not public holiday and not weekend).
Grace S
Apr 13, 2018Copper Contributor
Hi Sergei,
Thanks for the quick response. But in the formula stated that 1st Jan is a holiday hence I expect that the first working day is on the 2nd, and the next working day is the 3rd?
Grace