Action Planning with MS Project Pro
The simple answer is, there is NO connection between custom calendars. If you have a custom calendar for German holidays and it shows Jan 1 as a holiday, and you also have a custom calendar for Swiss holidays, which also has Jan 1 as a holiday, you must also list Jan 1 as a holiday exception on the Swiss calendar. Custom calendars are NOT related.
Resource calendars are defined by the resource's Base Calendar. The resource Base Calendar should show the Project Calendar, but if not edit it to agree with the Project Calendar. That way, the resource picks up all holidays.
However, a resource may have vacation days in addition to holidays. For that case, double click on the resource's name on the Resource Sheet. Then hit the "Change Working Time" button. Add unique exceptions as needed. For example, in this case Hans is taking vacation the week of August 11th.
Hope this further helps.
John