Earned Value Management - resource vs cost
I have a query and hoping someone is able to clarify, am I able to utilise plain cost to tasks instead of assigning resources with an hourly charge in order for earned value calculations to work? Instead of assigning a resource to a task in order for a cost to be set for the task, can I just add a cost to a task directly? I have tried to do this several times but I seem to keep getting no values for Cost Variance (CV), Schedule Variance (SV) is calculated but not CV. I am asking this as we are not able to add neither specific resources to tasks or have individual hourly costs to each resource and so this is not practical for us.620Views0likes1Comment