First published on TECHNET on Dec 15, 2016
This week saw the release of the December 2016 Public Update (PU) for Project Server 2010, 2013 and 2016. Client updates were released December 6th and server updates on December 13th. The client updates release in the first week of the month and server in the second week release schedule.
We are now delivering as Public Updates, although Server fixes are shipped just via the Download Center and not via Microsoft Update (Unless there is a security element or a fix deemed essential). These are still all cumulative and include fixes released in all previous updates since the last baseline (Initial release for 2016, SP1 for 2013 and SP2 for 2010).
Feel free to open a support case if you have any questions around this or need assistance getting these patches deployed.
One point to note is the installation of the Project Server 2016 package (SharePoint Server) for September 2016 and beyond can take longer to install than previous 2016 updates, on my slow server it took several hours, so you should ensure you test installation in a similar environment to production to ensure you allow enough downtime.
The 2013 PU releases also have a real prerequisite of the appropriate Service Pack 1 (SP1), and links for SP1 are given below. SP1 is enforced in this release, so you will find out (as I did) if you really do have SP1 for all your installed components and language packs! This also means RTM is no longer supported! See
http://blogs.technet.com/b/stefan_gossner/archive/2015/04/15/common-issue-april-2015-fixes-for-s...
too which describes an issue you might see if you don’t have the ‘right’ SP1. Slipstream would work with the original SP1 – but the updates require the re-released SP1. Since the May PU this shouldn’t be an issue – but including here just in case.
Another important point to add here is that there was in early 2013 running the SharePoint Configuration Wizard on a server with Project Server 2013 installed – this is fixed by applying the April 2013 or later– so a good practice would be to load SP1, then the current PU and then run the configuration wizard (if you didn’t already load the April 2013 through June 2014 CU).
This release for the 2010 products, like all 2010 patches since the December CU, has a hard requirement on Service Pack 2 – see notes below, (Support for Microsoft Office 2010 Service Pack 1 ended on 10/14/14). Don’t forget language packs SP2 if you have any language packs loaded! In most of the KB articles the term hotfix is used in place of Cumulative Update. They tend to be interchangeable terms – a Cumulative Update is just a hotfix built to a schedule. I should also point out that the individual Project Server packages are only ‘individual’ in the sense that they do not include the SharePoint patches – they are still cumulative and the December PU will contain all previous CU releases (at least back to the applicable baseline). Also worth noting that mainstream support for Project and Project Server 2010 ended October 13th 2015 – see
https://support.microsoft.com/en-us/lifecycle
Also a reminder – an SP1 patched 2010 system (with no SP2) is no longer supported – see the Lifecycle site for more information –
http://support.microsoft.com/lifecycle/search?sort=PN&alpha=project+2010&Filter=FilterNO
Project 2016
An overview of all the Office 2016 releases for December 2016 can be found here –
https://support.microsoft.com/en-us/kb/3208595
- December 13, 2016, update for Microsoft Office.
Project Server 2016
With the 2016 release we just have a single patch (but this month the single patch comes in two parts… a wssloc and sts2016 part). – as we have also the single msi for installation of SharePoint Server 2016 (Project Server still needs licensing separately though). Both parts need installing before the config wizard is executed.
December 13, 2016, update for SharePoint Server 2016 (KB3128014) -
Includes Project fixes, like the roll-up patch in Project Server 2013.
https://support.microsoft.com/en-us/kb/3128014
December 13, 2016, update for SharePoint Server 2016 (KB3128017) -
Includes Project fixes, like the roll-up patch in Project Server 2013.
https://support.microsoft.com/en-us/kb/3128017
There is a database schema update this month to 16.0.4471.1000. Remember, Project Server 2016 data is in the content database. The version number 16.0.4471.1000 can be used to control the connecting client to the December 2016 level. For reference – the RTM build number seen for the DB schema would be 16.0.4327.1000.
Project 2016 Client Package:
December 6, 2016, update for Project 2016 (KB3127994)
https://support.microsoft.com/en-us/kb/3127994
The version of Project Professional 2016 will be updated to 16.0.4471.1000 in the properties for WinProj.exe. However, I have noticed that in 2016 we don’t do a good job of displaying the version and in File, Account, About Project we only display the MSO version and not the specific Project version (You can confirm this by looking at the version of winproj.exe – in (default for 32 bit) C:\Program Files (x86)\Microsoft Office\Office16)
If you have Click to Run and using Project Pro for Office 365 at the ‘16’ level, then your version will depend on which update frequency you have set. Take a look at
https://blogs.office.com/2016/02/09/deferred-channel-build-now-available-for-the-office-365-clie...
for a few changes in this area – Current Branch for Business is now called Deferred Channel. We are aware that we don’t appear to expose the full change details for Project and are looking into it.
Project
and Project Server 2013
An overview of all the Office 2013 releases for December 2016 can be found here –
https://support.microsoft.com/en-us/kb/3208595
- December 13, 2016, update for Microsoft Office.
This include a number of fixes, so Microsoft strongly recommends that you test this in a test environment based on your production environment before putting this fix live in production.
The article below provides information on how to deploy the Project Server Cumulative Update.
You can read about the fixes included in the Project and Project Server December PUs from the following articles:
Project Server 2013 Server Rollup Package
December 13, 2016, cumulative update for Project Server 2013 (KB3128003)
https://support.microsoft.com/en-us/kb/3128003
Project Server 2013 Individual Project Package – (cumulative, but only the Project Server fixes):
December 13, 2016, update for Project Server 2013 (KB3128009)
https://support.microsoft.com/en-us/kb/3128009
There is a database schema update this month – so the dbo.Versions table should now show 15.0.4883.1000 after applying the December 2016 PU. The version number 15.0.4885.1000 can be used to control the connecting client to the December 2016 level.
SP1 for Project Server 2013 can be found here –
http://support.microsoft.com/kb/2880553
Project 2013 Client Package:
December 6, 2016, update for Project 2013 (KB3127978)
https://support.microsoft.com/en-us/kb/3127978
The client version number will be December 6, 2016, update for Microsoft Office. The server scheduling engine is no longer blocked by version control since the November 2014 CU on the server, so providing you have November 2014 CU or above on the server you can use the 15.0.4885.1000 value to control connection of the December 2016 PU patched client.
If you are running a server CU earlier than November 2014 CU, then follow the suggested version number for the server patch level you are running. See
Project Server 2013- Controlling the version of connecting clients–and PWA edits-
for more details. As mentioned above – the version number entered no longer controls the server side scheduling engine – so from the November 2014 CU release onward you can set a higher version to control clients without blocking the server side scheduling in the schedule web part.
SP1 for Project Professional 2013 can be found here –
http://support.microsoft.com/kb/2817433
Also note that Click to Run installations will be automatically patched. Installations in Enterprise Environments that have been modified will be deployed based on the schedule determined by your Administrator. See
http://support2.microsoft.com/gp/office-2013-click-to-run
. You may also choose to update your click to run Project Pro for Office 365 to the new 2016 level – this can still connect to Project Server 2013 – see the 2016 section above for current version.
Project and Project Server 2010
An overview of all the Office 2010 releases for December 2016 can be found here –
https://support.microsoft.com/en-us/kb/3208595
- December 13, 2016, update for Microsoft Office.
In general, updates include a number of fixes, so Microsoft strongly recommends that you install in a test environment based on your production environment before rolling out to a production environment.
Project Server 2010
NOTE: There are no Project Server specific updates in the Project Server roll-up for December 2016. The released rollup package contains security updates for SharePoint 2010, but no specific fixes for Project Server 2010 service application.
Project Server roll-up package
December 13, 2016, cumulative update for Project Server 2010 (KB3128033)
https://support.microsoft.com/en-us/kb/3128033
NOTE:
Although this patch is called an update for Project Server – and is what we would normally consider the ‘roll-up’ patch –
there are no
new
fixes for Project Server (hence no individual package).
This does however contain all the updates shipped up to the January update – so can be used to bring you right up to date with Project Server 2010 and the other products included in the roll-up patch.
Project 2010 Client Package:
There is no client package for Project Professional 2010 in December 2016.
Client Installation:
The instructions for installing the client patch are below.
NOTE: Microsoft strongly recommends testing within a NON-Production environment prior to rollout.
-
Download the hotfix from the link in the KB Article.
-
Extract the patch package by running the .exe file that you downloaded.
-
Run the extracted .exe file to apply the patch to your Project Professional/Standard client.
Or, from February 2015 onwards use Windows Update to download and install the patches.