wrong data
1 TopicTask Control - Actual Start and Actual Finish Wrong data
Hello team. Once again I very much want to receive your dear help. I have a work resource that has been allocated a task with 5% (11 mins) of its availability, in a 220 mins task. (...this task also has other work resources). In the task usage view, in the control table, this resource is updated with the actual work of 5 mins. It is from this moment that the calculations of real start and real end give me incorrect data. I would like to know why is this happening?2.1KViews0likes13Comments