elapsed day
1 TopicResource with elapsed days
Hello team . I have a uneasiness. If a 3.66 hour activity (09:00 – 13:00) with a 20-minute break. It has resources (People) that take the break and others don't (equipment), working in full for the total 4 hours of the activity. How can I configure this resource (equipment) to work the full 4 hours? Without affecting others or becoming undercharged.Solved1.2KViews0likes3Comments