Azure DevOps Capacity Planning for 2 Weeks Sprint

Copper Contributor

Hello,

I have a typical situation. My sprints are of 2 weeks time (Ex: 08/14/2023 to 08/25/2023).

Dev-1 started from Day-1 and for 1st week we need his 6.5 Hrs per day but for the 2nd week, we need his 3.5 Hrs per day.
Dev-2 started from 2nd week in the team and his capacity should be 3.5 hrs per day.

For Dev-2 it is easy as we can make his off day for the 1st week.
But not sure how to configure for Dev-2. Please suggest.

Thanks,

Prabhat

1 Reply
best response confirmed by Prabhatnath (Copper Contributor)
Solution
The sprint capacity breaks down by day, but the work detail totals the capacity to the current date.
Dev 1 has a total capacity of 50 hours for the sprint (3.5 *5) + (6.5*5). Divide 50 by 9 days and that's 5.5 hours per day with one day off. Enter the day off in the days off column.
Dev 2 has five days off this sprint. Enter the days off in the days off column. The other days the dev is working 3.5 hours per day.
1 best response

Accepted Solutions
best response confirmed by Prabhatnath (Copper Contributor)
Solution
The sprint capacity breaks down by day, but the work detail totals the capacity to the current date.
Dev 1 has a total capacity of 50 hours for the sprint (3.5 *5) + (6.5*5). Divide 50 by 9 days and that's 5.5 hours per day with one day off. Enter the day off in the days off column.
Dev 2 has five days off this sprint. Enter the days off in the days off column. The other days the dev is working 3.5 hours per day.