Azure DevOps Capacity Planning for 2 Weeks Sprint
Hello, I have a typical situation. My sprints are of 2 weeks time (Ex: 08/14/2023 to 08/25/2023). Dev-1 started from Day-1 and for 1st week we need his 6.5 Hrs per day but for the 2nd week, we need...
- Aug 30, 2023The sprint capacity breaks down by day, but the work detail totals the capacity to the current date.
Dev 1 has a total capacity of 50 hours for the sprint (3.5 *5) + (6.5*5). Divide 50 by 9 days and that's 5.5 hours per day with one day off. Enter the day off in the days off column.
Dev 2 has five days off this sprint. Enter the days off in the days off column. The other days the dev is working 3.5 hours per day.
elieade
Aug 30, 2023Brass Contributor
The sprint capacity breaks down by day, but the work detail totals the capacity to the current date.
Dev 1 has a total capacity of 50 hours for the sprint (3.5 *5) + (6.5*5). Divide 50 by 9 days and that's 5.5 hours per day with one day off. Enter the day off in the days off column.
Dev 2 has five days off this sprint. Enter the days off in the days off column. The other days the dev is working 3.5 hours per day.
Dev 1 has a total capacity of 50 hours for the sprint (3.5 *5) + (6.5*5). Divide 50 by 9 days and that's 5.5 hours per day with one day off. Enter the day off in the days off column.
Dev 2 has five days off this sprint. Enter the days off in the days off column. The other days the dev is working 3.5 hours per day.