Azure DevOps Capacity Planning for 2 Weeks Sprint

Hello, I have a typical situation. My sprints are of 2 weeks time (Ex: 08/14/2023 to 08/25/2023). Dev-1 started from Day-1 and for 1st week we need his 6.5 Hrs per day but for the 2nd week, we need...
  • elieade's avatar
    Aug 30, 2023
    The sprint capacity breaks down by day, but the work detail totals the capacity to the current date.
    Dev 1 has a total capacity of 50 hours for the sprint (3.5 *5) + (6.5*5). Divide 50 by 9 days and that's 5.5 hours per day with one day off. Enter the day off in the days off column.
    Dev 2 has five days off this sprint. Enter the days off in the days off column. The other days the dev is working 3.5 hours per day.