P4W observation: although the new Assignments view is great within the scheduling UI, the daily PlannedEffort of a resource is not available for reporting. The msdyn_plannedwork (json) field within the msdyn_resourceassignment table in dataverse, in fact, contains RemainingWork/Effort and NOT PlannedWork/Effort. When will timephased datasets for PlannedWork/Effort be made available for reporting. We cannot generate planned Availability or Utilization without it. tx