Are there any plans to be able to add external resources as assigned personnel to Planner tasks? Such as if I want to track project action items that are the responsibility of the Customer to complete? It would be great to be able to tag both myself and a customer, external resource name on such action item Planner tasks.
- DanEngelsmeierMay 10, 2023Brass ContributorWe do this by inviting the external resource as a "guest" user in our tenant. They are added to the relevant Microsoft Team and access their Planner tasks through there.
- Brian-SmithMay 10, 2023Bronze ContributorThis should work if the external resource is known to your system John - unless you have it locked down in some way.
- John_HooverMay 10, 2023Iron ContributorMy organization has very strict security controls because of the nature of our work. Getting someone added as a "guest" is a very high lift. Ideally it would be possible to simply create a "generic" or "material" resource that I can custom name and add to the Planner plan without needing to add a full profile of any kind.