My other question just got lost, but my Tasks in New Planner in Teams only allows the update of Progress on a Task from Project for the web that has effort. To update Effort, you have to click on the Project for the web Project link to update Effort and Work Remaining in Project for the web? Is this intended behavior?
- Brian-SmithApr 04, 2024Former EmployeeThat is the current intended behavior Alicia. If you open up the plan from My Plans you would be able to add the effort and remaining effort columsn to make such an update, but initially the columns available in My Tasks for premium plans are similar to those of basic plans.