Hi,   We've noticed that for one of our Azure DevOps Project, the Sprint Taskboard is showing two (2) additional Statuses/Columns but they are unusable (e.g. unable to drag Task cards into those co...
  • Thaddee Bourque's avatar
    Dec 19, 2018

    Hi,

     

    I have resolved my own issue.  It was due to a disabled Work Item Type associated to the Iteration Backlog under the process' Backlog Level configuration.  Even though the Work Item Type was disabled, it's statuses were still showing up in the Sprint Taskboard.  Once I removed it from the Iteration Backlog, the extra columns were gone.

     