I can see this update on planner, however when I create a template using the project manager, the "schedule" view tab is no longer there, nor any other tab that has a timeline view such as "timeline" or "gantt" etc...
Those are clearly shown in the demo video attached in this blog... What am I doing wrong?
Sounds like you are creating a basic plan. If you create a premium plan you should see those tabs. Do you have any Planner licenses applied to your account 1/3/5 - if so you should see the option to create plans that are more than basic.
- DrSaeedAljneibiApr 02, 2025Copper Contributor
That's the weird part, when I do "Basic", I can see a "Schedule" view, but when I choose "Project Manager", I can see premium features such as dependencies and so on, but no timeline/schedule view.
However, I only have either "Basic" or "Project Manager" but no "Premium"...